One-minute source brief
B.C. court quashes KSM’s substantially started designation
The B.C. Supreme Court quashed the finding that Seabridge Gold’s KSM project was substantially started. The province has to reconsider the designation. Seabridge says the mine’s legal status has not changed.
Canadian Mining Journal · Original publisher source · Source release: 2026-11-23

The designation is back with the province
Canadian Mining Journal reported that the B.C. Supreme Court quashed KSM’s substantially started status and told the province to reconsider it. In 2024 an assessment officer had ruled the project substantially started, which would have let it keep its environmental approvals. In June 2026 the court found the province had not properly consulted the Tsetsaut Skii km Lax Ha Nation. [1]
What each side said
Seabridge chair and chief executive Rudy Fronk said the company is confident KSM has met the test for a substantially started designation, and that the mine’s legal status has not changed. Counsel for the Nation, Ryan Beaton, said the decision matches the Nation’s view that Seabridge and the province had been downplaying the court’s earlier ruling. [1]
The project and the share move
KSM is 65 kilometres northwest of Stewart, B.C. Seabridge calls it one of the world’s largest undeveloped gold projects. A 2022 preliminary feasibility study put reserves at 47.3 million ounces of gold and 7.3 billion pounds of copper, with a net present value of $7.9 billion. Canadian Mining Journal reported the shares closed Thursday at $25.92, down 29.26 percent from $36.64, then fell further on Friday and regained 12.10 percent Monday morning. [1]
Sources & footnotes
- Canadian Mining Journal · 2026-11-23 · B.C. court quashes KSM’s substantially started designation. Checked 2026-11-23.