Lithium Americas lifts Thacker Pass Phase 1 cost estimate to $3.83 billion
Lithium Americas raised the estimated first-phase cost of Thacker Pass in Nevada by 31% and said it still targets commercial production in 2028.
Canadian Mining Journal · Original publisher source · Source release: 2026-11-11

Cost estimate rises and funding need grows
Lithium Americas raised the estimated cost of Phase 1 at Thacker Pass by 31% to $3.83 billion, citing higher labour, construction and logistics expenses. The revised budget adds $895 million in capital costs and increases the project's funding requirement by about $995 million. The company said it expects to cover the extra amount through contributions and available DOE loan reserves. [1]
Construction timing and output targets stay in place
The company said Phase 1 is advancing toward peak construction activity by year end 2026, with mechanical completion targeted for late 2027. It continues to target commercial production in 2028. Phase 1 is designed to produce 40,000 tonnes of battery-grade lithium carbonate annually at full capacity, and the project is expected to supply lithium for about 1 million electric vehicles annually. [1]
Higher labour and tariff pressures weigh on market sentiment
Higher labour installation rates for piping, steel and equipment accounted for $245 million of the increase, while tariffs and logistics added approximately $100 million. Investors reacted negatively, sending Lithium Americas shares down almost 8% to C$2.48 and cutting its market capitalization to nearly C$544 million. The company held about $1.3 billion in cash and restricted cash as of Sept. 30. [1]