Vizsla pushes Panuco first silver target to second-half 2028
Vizsla Silver delayed first production at Panuco by a year after the January abductions and killings in Sinaloa. The company says engineering is about halfway complete, most plant equipment is ordered, and it is pursuing a phased return while approvals remain outstanding.
Canadian Mining Journal · Original publisher source · Source release: 2026-11-19

Production target slips to second-half 2028
Vizsla Silver said it has pushed back first production at Panuco by a year and now targets first silver in the second half of 2028. The revised schedule reflects permitting, site readiness and construction timing. The company is preparing a phased return to the Mexico site after security disruptions linked to the January case in Sinaloa. [1]
Engineering progress and plant orders
Vizsla says engineering is about halfway complete and about 85% of the planned processing plant equipment has been ordered. Its current mine plan calls for two underground mines, Copala and Napoleon, feeding a single plant. The November 2025 feasibility study outlined initial capital of US$238.7 million and projected payable output over 9.4 years. [1]
Approvals, investigation and community response
Panuco still needs key federal approvals, including a land-use change authorization, and Vizsla has not yet made a production decision. The company says it continues to assist the investigation into the abductions and killings of 10 workers. It has committed US$5 million to a Sinaloa foundation and plans to add a share of future profits. [1]
Sources & footnotes
- Canadian Mining Journal · 2026-11-19 · Vizsla delays first silver at Panuco by a year. Checked 2026-11-20.