Nexus Uranium reports Chord permitting progress and U.S. policy support
Nexus Uranium says an appeal was dismissed at Chord, while state and federal permitting continue. The company also highlighted U.S. critical-mineral policy support, a House vote on uranium enrichment licensing, and HoldCo Markets research coverage as part of its investor-awareness program.
Mining Stock Education · Original publisher source · Source release: 2026-11-16

Appeal dismissal narrows a state-process issue at Chord
Nexus Uranium says the Eighth Circuit affirmed dismissal of an intervenor action tied to Lakota-language interpretation at the Chord Project’s state contested case hearing. The company says that removes an open question in the state process, but the hearing remains suspended and no resumption date has been set. Nexus continues working with the Board and state agencies. [1]
State and federal permitting both remain in progress
Chord still requires two permitting tracks: a South Dakota state process and a federal review for National Forest System land. Nexus says it submitted a Plan of Operations in June 2024, a revised plan in October 2024, signed an MOU in July 2025, and entered FAST-41 review in January 2026. The company says it will provide a maiden drill schedule after permits. [1]
Company points to supportive U.S. policy and research coverage
Nexus frames recent U.S. actions as favorable to domestic uranium, citing critical-mineral designation, mining and processing investments, workforce funding, and the House passing H.R. 9612 on uranium enrichment licensing. The company says HoldCo Markets published initiation coverage on October 22, 2026, but notes the report is HoldCo Markets’ own view and was not verified by Nexus. [1]