Mine Development

One-minute source brief

Amex advances Perron ramp and starts power-line construction

Infrastructure work supports the planned bulk sample as underground access continues to develop.

Amex Gold Mining Inc. · Original issuer source · Source release: 2026-11-19

Original issuer photograph of electrical posts being loaded for the Perron power line.
Electrical posts loaded for Perron power-line installation. Credit: Amex Gold Mining Inc. · Original image source · View source image at full size ↗

What changed

Amex Gold Mining reported 200 metres of completed underground ramp development at its Perron Gold Project near Normétal, Québec. The work advances access for the company's fully funded 40,000-tonne bulk sample program. Construction has also started on the power line connecting the project with the local electrical grid. [1]

Infrastructure progress

The planned connection is approximately 6.5 kilometres long and rated at 25 kilovolts, with capacity intended for both the bulk sample and the proposed first mining phase. Amex says the mechanical garage structure and permanent underground ventilation system have been installed. Other site facilities are nearing completion. [1]

The remaining steps

These are construction milestones on the way to collecting the bulk sample. They do not mean the sample is complete or that commercial mining has begun. Continued ramp development, site completion and electrical work will determine readiness for the next operating steps. The release reports infrastructure progress while the project continues toward its planned development objectives. [1]